Which document is best suited for tracking the assignment of all resources to specific tasks in a project?

A.
RACI mAl,x

B.
sow

C.
Staffing management plan

D.
CPI

Explanation:
The RACI matrix lists responsibilities of all resources. The staffing management plan only lists types of resources and timing.