Where should the declined change request be documented and stored?

[tagged]
You work as a project manager for BlueWell Inc. You have declined a proposed change request
because of the risk associated with the proposed change request. Where should the declined
change request be documented and stored?

A.
Change request log

B.
Lessons learned

C.
Project archives

D.
Project document updates