PMI Exam Questions

what you tell ?

Is a project with a SPI of 1.8, what you tell ?

A.
The project is runnig ahead of the schedule

B.
The project is running behind of the schedule

C.
Resources assigned to the project cost 1.8 units

D.
None

Explanation:
The SPI= EV/PV. A schedule performance Index of 1 or greater suggests that the project is aahead of schedule.