What should be your concern? seenagape 12 years ago Your project has an EV of 100 work-days, an AC of 120 work days, and a PV of 80 work days. What should be your concern? A.There is a cost under run B.There is a cost overrun C.May not meet deadline D.The project is 20 days behind schedule ← Previous question Next question →