PMI Exam Questions

What is the schedule variance for this project that Fred needs to report to the management?

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty
percent complete. Fred has crashed the project, which has driven the project costs to date to
$1,525,140, but his project is five percent more complete than what was planned. What is the
schedule variance for this project that Fred needs to report to the management?

A.
$176,675

B.
$122,845

C.
-$85,000

D.
-$51,000

Explanation:
There is positive variance of $122,845 on Fred’s project. Variances can be either positive or
negative. Schedule variance (SV) is a measure of schedule performance on a project. The
variance notifies that the schedule is ahead or behind what was planned for this period in time.
The schedule variance is calculated based on the following formula: SV = Earned Value (EV) -Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind
schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value
of 0 indicates that the project is right on target.
Answer option C is incorrect. This is the project’s variance at completion.
Answer option D is incorrect. This is the cost variance for the project.
Answer option A is incorrect. This is not a valid answer for the project.