What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) seenagape 8 years ago What is the schedule performance index (SPI) if the planned value (PV) is $100, theactual cost (AC) is $150, and the earned value (EV) is $50? A. 0.50 B. 0.67 C. 1.50 D. 2.00 ← Previous question Next question →