What is the LEAST likely cause of the slippage?

The Java development of a project is outsourced to India. The project schedule is starting to slip.
What is the LEAST likely cause of the slippage?

A.
Lack of competent programmers

B.
Cultural influences

C.
Internationalization

D.
Communication