What is the estimate at completion (EAC) if the budget at completion (BAC) is $100,
the actual cost (AC) is $50, and the earned value (EV) is $25?
A.
$50
B.
$100
C.
$125
D.
$200
Explanation:
EAC=BAC/CPI and CPI=EV/AC
CPI = EV/ AC = 25/50 = 0.5
EAC = BAC/ CPI = 100/0.5 = $200