You are the project manager of the NHQ Project. Management has set a conformance to the
project schedule for your project at 0.95. What does this term mean?
A.
It means the largest schedule variance you can have is five percent.
B.
It is the earned value divided by the planned value for your project.
C.
It is the expectation of management to be 95 on schedule at 95 percent of the project.
D.
It means you will need to earn at least 95 cents per dollar invested in the project.
Explanation:
Conformance to schedule is a required adherence for the project’s schedule. In this instance, the
project manager must not allow the schedule to slip more than five percent.
Answer option B is incorrect. This is the description of the schedule performance index.
Answer option D is incorrect. This is the description of the cost performance index.
Answer option C is incorrect. This is not a valid statement about the project performance.