PMI Exam Questions

The project baseline is _______.

The project baseline is _______.

A.
Original plans plus the approved changes

B.
Important in the project initiation phase

C.
Initial estimates for tasks and resource utilization

D.
Original plans and the approved major changes

Explanation:
The project baseline: original plans plus the approved changes.