PMI Exam Questions

The __________ includes a description of any collateral services required, such as performance repor

CORRECT TEXT
Fill in the blank with an appropriate phrase.
The __________ includes a description of any collateral services required, such as performance
reporting or post-project operational support for the procured item.

Answer: procurement SOW