Resource reallocation from non critical to critical activities is an example of which of the followi

Resource reallocation from non critical to critical activities is an example of which of the following Project Scheduling technique:

A.
Resource Leveling

B.
Schedule Compression

C.
Critical Path Method

D.
What if Analysis

Explanation:
Resource Leveling :Allocate scare resources to critical path activities first .