What is your COST Variance percentage in this case?
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, the work is on schedule, but you have spent $120,000 of the project budget. What is your COST Variance percentage in this case?
Which characteristic distinguishes the network diagram from the Gant chart?
Which characteristic distinguishes the network diagram from the Gant chart?
Which of the following tools and techniques are commonly used in a Define Scope Process?
Which of the following tools and techniques are commonly used in a Define Scope Process?