Which of the following statements best describes the influence of stakeholders and the cost of chang

Which of the following statements best describes the influence of stakeholders and the cost of changes as

project time advances?

A.The influence of the stakeholders increases, the cost of changes increases.

B.The influence of the stakeholders decreases, the cost of changes increases.

C.The influence of the stakeholders increases, the cost of changes decreas

es.

D.The influence of the stakeholders decreases, the cost of changes decreases.