Activity resource requirements and the resource breakdown structure (RBS) are outputs of which P&#82

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which P

roject Time Management process?

A.Control Schedule

B.Define Activities

C.Develop Schedule

D.Estimate Activity Resources