Based on the PMBOK, who is ultimately responsible for the project quality?

Based on the PMBOK, who is ultimately responsible for the project quality?

A.
Project team

B.
Project manager

C.
QA manager

D.
Validation engineer

Explanation:
Project manager IS ultimately responsible for the project quality