A major assumption of all network schedulling methods is that the activity duration must be ________ seenagape 11 years ago A major assumption of all network schedulling methods is that the activity duration must be ________________ A.Statistically dependent B.Variance distributed C.Statistically independent D.Deterministic ← Previous question Next question →