HP Exam Questions

What is the preferred time for completing racking and labeling of equipment for a new implementation

What is the preferred time for completing racking and labeling of equipment for a new
implementation?

A.
After the scheduled outage has begun and initial tests have indicated success

B.
Before the scheduled outage

C.
At any time between the beginning of the scheduled outage and the point of no return

D.
At the beginning of the scheduled outage

Explanation: