VMware Exam Questions

Which two steps must be taken to ensure a successful NSX deployment?

A data center environment contains the following:
VMware vCenter 5.1
ESXi hosts 4.1 and higher
VMware Horizon View 5.2
Network devices with merchant silicon ASICs
Which two steps must be taken to ensure a successful NSX deployment? (Choose two.)

A.
Upgrade the vCenter Server installation to vCenter Server 5.5.

B.
Upgrade the network devices to support layer 2 multi-pathing.

C.
Upgrade all compute nodes to ESXi 5.1 or later.

D.
Upgrade the VMware Horizon View installation to Horizon View 5.3.