PrepAway - Latest Free Exam Questions & Answers

which of the following should be considered?

When considering incorporating redundancy into design, which of the following should be

considered?

PrepAway - Latest Free Exam Questions & Answers

A.
The impact of the failure

B.
The likelihood of the failure

C.
RTO and RPO values

D.
All of these are correct

Explanation:

The recovery time objective (RTO)—also known as the return to operation—is the amount of timeit
takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the
point intime to which the system needs to be restored following a failure. In some cases a
business may beinterested in functionality and just assume items such as redundancy. The
infrastructure qualities helpconsider aspects considered as good design.