What is the best practice workflow for a NSX installation to support logical switching?

A.
Deploy NSX Manager, Configure Logical Switches, Register with vCenter, Deploy Controllers. Prepare
hosts
B.
Deploy NSX Manager, Deploy Controllers, Configure Logical Switches, Register with vCenter, Prepare
hosts
C.
Deploy NSX Manager, Register with vCenter, Prepare hosts, Deploy Controllers, Configure Logical
Switches
D.
Deploy NSX Manager, Register with vCenter, Deploy Controllers, Prepare hosts, Configure LogicalSwitches
I would rather say C cause it’s the procedure used to install NSX
https://docs.vmware.com/en/VMware-NSX-for-vSphere/6.2/nsx_62_install.pdf
1
4
You’re right it is B
0
3
According to the NSX 6.2 Design Guide Graph on page 14, the order is as follows:
1. Deploy NSX Manager.
2. Register NSX Manager with vCenter.
3. Deploy NSX Controllers.
4. Prepare Hosts.
5. Deploy & Configure NSX Edge GW(s), and configure network services.
6
0
So then, Option “D”, would be correct – according to the design guide.
5
0
The correct answer is D
4
0
I would concur with D.
3
0
D is correct.
http://www.vmwarearena.com/wp-content/uploads/2015/01/NSX-Installation-Order-of-Tasks.jpg
2
0
Concur with D
1
0
D is absolutely correct as it is clearly mentioned on VMware NSX Docs
0
0
What’s more, part of that new 313Q 2V0-642 dumps are available here:
https://drive.google.com/open?id=0B-ob6L_QjGLpbVl3X1hXbUdteHc
Best Regards!
0
1
The correct answer is D. You cannot deploy Controllers with out being registered to vCenter
0
0
Correct answer is D, because I read it during my stay at the Kamar Taj
0
2