How can the restart of VMs after a failure be automated?

You are planning a large virtualization project and are concerned that a physical server will cause
a prolonged outage until help desk calls are received and all VMs restarted. How can the restart of
VMs after a failure be automated?

A.
Fault Tolerance (FT)

B.
High Availability (HA)

C.
Data Protection

D.
Distributed Resource Scheduler (DRS)

Explanation:
Reference:http://www.vmware.com/files/pdf/VMware-High-Availability-DS-EN.pdf