Briefing Veritas Knowledge

How is the migration completed?

The following steps for migrating an application from system S1 to S2 have been completed on S1: unmount the file system stop the volume deport disk group How
is the migration completed?

A.
(on S2) rescan; import disk group; start volume; mount file system; start application

B.
(on S2) rescan; import disk group with -n option; start volume; mount file system; start application

C.
(on S2) import disk group with -h option; start volume; mount file system; start application

D.
(on S2) import disk group with -startall option; mount file system; start application