Which of the following statements about TOGAF Building Blocks and their use in the ADM cycle is correct?

A.
Building Blocks become more implementation-specific in Phase E
B.
Building Blocks should be first selected in Phase D
C.
Building Blocks in phases D, E and F are evolved to a common pattern of steps
D.
Building Blocks should be identified in abstract form as part of the Preliminary Phase