Which of the following is not part of a Request for Architecture Work document?

2.5: Which of the following is not part of a Request for Architecture Work document?

A.
Budget and financial constraints

B.
Time constraints

C.
Gap analysis

D.
Business goals and desired changes

E.
Current IT architecture description