Briefing The Open Group Knowledge

Which of the following is not an output from Phase E?

1.E.6: Which of the following is not an output from Phase E?

A.
Project list

B.
Implementation and migration strategy

C.
High level implementation plan

D.
Impact analysis

E.
Detailed implementation plan