Briefing The Open Group Knowledge

Which of the following is not a key input into Phase G – Implementation Governance?

1.G.1: Which of the following is not a key input into Phase G – Implementation Governance?

A.
Statement of architecture work

B.
Competitive analysis reports

C.
Request for architecture work

D.
Reusable solution building blocks

E.
Impact analysis