Which of the following describes the Phase H classification for an Incremental change?

A.
A change driven by a requirement to reduce investment
B.
A change driven by a requirement to re-align with the business strategy
C.
A change driven by a requirement to increase investment in order to create new value for
exploitation
D.
A change driven by a requirement to derive additional value from the existing investment
D. (16.2.2)