Which of the following describes the Phase H classification for an Incremental change?

A.
A change driven by a requirement to derive additional value from the existing investment
B.
A change driven by a requirement to increase investment in order to create new value for
exploitation
C.
A change driven by a requirement to reduce investment
D.
A change driven by a requirement to re-align with the business strategy
I agree with the answer. A
0
0
16.2.2 Enterprise Architecture Change Management Process
Incremental change: an incremental change is dr iven by a requirement to derive additional value from existing investment