What document is sent from the sponsoring organization to the architecture organization to trigger
the start of an ADM cycle?

A.
Architecture Contract
B.
Architecture Definition Document
C.
Architecture Vision
D.
Request for Architecture Work
E.
Statement of Architecture Work
TOGAF 9.1 book, section 7.2.1 – “Phase A starts with receipt of a Request for Architecture Work from the sponsoring organization to the architecture organization.”
The correct answer is D.