Complete the sentence. The Requirements Management process is used to______.

A.
develop requirements for Transition Architectures that deliver business value
B.
dispose of, address and prioritize architecture requirements
C.
organize architecture requirements throughout the ADM cycle
D.
review business requirements
E.
validate requirements between ADM phases
TOGAF 9.1 book, section 17.1 – Manage architecture requirements identified during any execution of the ADM cycle or a phase
The answer is C.