which of the following is the best answer?

Scenario:
Please read this scenario prior to answering the Question
You are serving as the Chief Architect for a large, global commodities trading company which has been growing
rapidly through a series of acquisitions.
Each business is performing well in its markets. However, the lack of integration between headquarters and the
business units has increasingly caused problems in the handling of customer and financial information. The
inability to share information across businesses has resulted in lost opportunities to “leverage the synergies”
that had been intended when the businesses were acquired. At present, each business unit maintains its own
applications. Despite an earlier initiative to install a common application to manage customer, products,
supplier, and inventory information, each business unit has different ways of defining each of these core
elements and has customized the common application to the point where the ability to exchange information is
difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate
information from several applications that exist across the lines of business. The application will be used by all
business units and accessed by suppliers through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential
customer information in a secure manner that meets or exceeds the legal requirements of the countries in
which the company operates. This will be an increasingly important capability as the company expands its
online services in cooperation with its trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to
coordinate efforts between the implementation team and the business unit personnel who will be involved in the
migration process. The CIO has also formed a cross-functional Architecture Board to oversee and govern the
architecture. The company has an existing team of security architects.
TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has endorsed this choice
with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate
capability to address the concerns of the Corporate Board.
Based on TOGAF 9, which of the following is the best answer?

which of the following is the best answer?

Scenario:
Please read this scenario prior to answering the questionYou are the Lead Enterprise Architect in a company that specializes in the development of wind turbine blades
for use in large-scale commercial wind energy production systems. The company has manufacturing facilities
located in Illinois, Nebraska, and Manitoba. Each of these plants supplies a different manufacturer that builds
and sells complete systems. The turbine blades are custom engineered to meet each manufacturer’s design
specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However,
recent improvements in composite materials, coupled with enhanced automated methods for precision
application of materials during the molding process, have led to significant reduction in weight, increase in
strength, and improved blade longevity. The company has pioneered the development of a proprietary
automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the
process, but certain trade secrets must be closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a cross-functional
Architecture Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise
Architecture program.
TOGAF 9 and its Architecture Development Method (ADM) are used to develop the automated manufacturing
processes and systems that are used to design, manufacture, and test the blade assemblies.
Recently, a pilot architecture project was completed at a single location that defined a standard approach for
controlling the Automated Test System that is used at each plant to perform final quality assurance tests on
each completed blade assembly. The Architecture Board approved the plan for immediate implementation at
each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new
Automated Test System controller for each location. The Chief Engineer, sponsor of the activity, has expressed
concern that a uniform process be employed at each location to ensure consistency.
Refer to the Scenario
You have been asked to recommend the best approach to address the Chief Engineer’s concern.
Based on TOGAF 9, which of the following is the best answer?

which of the following is the best answer?

Scenario:Please read this scenario prior to answering the Question
You have been appointed as a consultant to the Lead Enterprise Architect of an international agricultural
company that exports bulbs, flowers and seeds worldwide. The company has its headquarters in the
Netherlands, and has sales and distribution centers in over 30 countries worldwide. Several of these centers
include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in various
climate zones, the company wants to develop strong self-directed teams in each location. It also wants to
define new business models that are profitable while reducing their impact on the environment. The
management team is deeply committed to ensuring that the company is a world leader in socially responsible
seed development with a business strategy that focuses on profitability through environmentally friendly
operating processes.
The international operations of the company are subject to legal and regulatory requirements for each country
where they operate. The production of genetically modified seeds has governmental controls that are strictly
enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a
country where it was developing pest-resistant seeds.
The Governing Board is concerned about the risks posed in this complex global environment, and as a result
has approved the expenditure of resources to establish an Enterprise Architecture program. They have
requested to be informed about the status of projects that could impact regulatory compliance. They also want
to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within
the legal guidelines for a given location. In addition, the research organization should be able to see that the
architecture is appropriate for its needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise
Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture
capability for this project.
Refer to the Scenario
You have been asked to recommend an approach that would enable the development of an architecture that
addresses the needs of the Governing Board, legal staff, auditors and the research organization.
Based on TOGAF 9, which of the following is the best answer?

Which procurement-related business processes are suppor…

Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for the enterprise architecture team at the prime contractor for the
Dreadnought Unmanned Aircraft System program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous
different procurement processes and related IT systems. The decision has been made to consolidate andreduce redundant procurement processes and systems. The CEO has announced that the company will seek
to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier
program.
TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for executing
Architecture Development Method (ADM) projects.
At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be
acquired and customized or created from scratch. The company prefers to implement commercial off the shelf
package applications with little customization. The CIO, who is the project sponsor, has stated that she is not
concerned about preserving existing processes or systems.
The architect-re development project has put in place Its Architecture Capability for this project and has started
a number of iteration cycles to develop the Architecture. Some tasks to address concerns related to the
Business Architecture have been completed. The next immediate task is to address the Information Systems
Architectures.
The Information Systems Architectures must address stakeholder concerns such as:
1. Which procurement-related business processes are supported by zero, one, or many existing applications?
2. What non-procurement applications will need to be integrated with any new procurement applications?
3. What data will need to be shared?
Refer to the Scenario
[Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]
You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.
Based on TOGAF 9, which of the following is the best answer?

which of the following is the best answer?

Scenario:
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a company that manufactures a variety of small
electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, the company has defined
a strategic architecture to improve its ability to meet consumer demand and improve its ability to manage its
supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning
(ERP) applications that have been operating independently in several of the divisions’ production facilities. The
goal is to replace the functionality of the existing applications with a new ERP product running as a single
instance in the company’s primary data center.
The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its architecture
framework. In addition to the EA program, the company has a number of management frameworks in use,
including business planning, portfolio/project management, and operations management. The EA program is
sponsored by the CIO.Each division has completed the Architecture Definition documentation required to tailor and configure the
environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A
consolidated gap analysis has been completed which has identified the gaps across the Business, Data,
Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed
the requirements, dependencies and interoperability requirements needed to integrate the new ERP
environment into the existing environment. The architects have completed the Business Transformation
Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk
assessment.
Because of the risks posed by the complexity of the current environment, it has been determined that a phased
approach is needed to implement the target architectures. The overall implementation process is estimated to
take several years.
Refer to the Scenario
The Implementation and Migration Plan v0.l, the draft Architecture Roadmap, and the Capability Assessment
deliverables are now complete. You have been asked to recommend the next steps to prepare the final
Implementation and Migration Plan.
Based on TOGAF 9, which of the following is the best answer?

which of the following is the best answer?

Scenario: AGEX Inc.
Please read this scenario prior to answering the question
AGEX is a large, global commodities trading company which has been growing rapidly through a series of
acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters
and the business units has increasingly caused problems in the handling of customer and financial information.
The inability to share information across businesses has resulted in lost opportunities to “leverage the
synergies” that had been intended when the businesses were acquired. At present, each business unit
maintains its own applications. Despite an earlier initiative to install a common application to manage customer,
products, supplier, and inventory information, each business unit has different ways of defining each of these
core elements and has customized the common application to the point where the ability to exchange
information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to
consolidate information from several applications that exist across the lines of business. The Corporate Board
is concerned that the new ERP system must be able to manage and safeguard customer information in a
manner that meets or exceeds the legal requirements of the countries in which the company operates. This will
be an increasingly important capability as the company expands its online services offered to clients and trading
partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to
coordinate efforts between the ERP implementation team and the business unit personnel who will be involved
in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee
and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has
selected TOGAF 9 as the basis for its Enterprise Architecture program.The CIO has endorsed this choice with the full support of top management.
Refer to the AGEX Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided to create a set
of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?

which of the following is best answer?

Worldwide Mobile is a mobile telecommunications company formed through a series of mergers and
acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and
as result, customer service has been a major concern for the Chief Technology Officer.
Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer
retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published
some new finding about customer satisfaction. The customers appear to be switching to Air Light, a competitor,
because of superior customer service. WorldwideMobile actually has better coverage in nearly all markets than
Air Light, and good roaming agreement that keep rates low for business travellers. But customer satisfaction
has remained low.
The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to
develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good
conceptual model of what needs to be done and also identifies the key requirements. This was used in
preparing the proposal presented to the Executive Council and the Corporate Board.
The planning for the program has been underway for several months. WorldwideMobile has selected TOGAF 9
as the basis for its Enterprise Architecture.
The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged
Customer Service System. It is anticipated that the overall program will take five years to complete, but there
are some tactical projects that can commence immediately to address the situation. The Executive Council has
stated that the program should define specific initiatives to enable each regional business units to create an
implementation of the Customer Service System. The implementation must meet the needs of the business unit
and still provide the information needed to enable major improvements to the customer.
Refer to WorldwideMobile-2 Scenario
You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service
System program.
The project has been chartered to address the architecture(s) required to support the Customer Service
System from an infrastructure perspective. At present time, the project team is conducting an architecture
development project that is focused on the customer self service capability, which was defined as part of the
earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills,
request account reviews, and provision services from any web-enabled device.
The project team has gathered information about the self-service capability, developed a business scenario,
and used the results to define an Architecture Vision for achieving the capability.
You have been asked to recommend the course of action to complete the project.
Based on TOGAF 9, which of the following is best answer?

which of the following is the best answer?

Scenario: Vittronics Ltd.
Please read this scenario prior to answering the question
Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache
Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a
precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the
onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to
be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and
safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in
the target markets.
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to
create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product
development laboratories worldwide to share information about their independent clinical trials.
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several
years. They have recently upgraded to TOGAF 9. The Vittronics Architecture Development Method (VADM) is
strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support
current good manufacturing practices and good laboratory practices in their target markets.
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture
phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of
the information that is managed in SPICE, special care was taken to ensure that each architecture domain
included an examination of the security and privacy issues that are relevant for each domain. A corresponding
SPICE Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. He has
stated that the changes to the SPICE architecture will need to be rolled out on a geographic basis that will
minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in
geographical regions.
Refer to the Vittronics Ltd Scenario
You are serving as the Lead Architect for the SPICE project team.
You have been asked to recommend the approach to identify the work packages that will be included in the
Transition Architecture(s).
Based en TOGAF 9, which of the following is the best answer?

which of the following is the best answer?

Scenario: Rollins Manufacturing
Please read this scenario prior to answering the question
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio withmanufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been
operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom
developed applications that drive the automated production equipment at each plant.
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its
production operations. During a recent exercise held for internal quality improvement, it was determined that a
significant reduction in process waste could be achieved by replacing the current MRPII and scheduling
systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This
central system would provide support to each of the plants replacing the functionality in the existing systems. It
would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff
could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Rollins Enterprise Architecture department has been operating for several years and has mature, welldeveloped architecture governance and development processes that are strongly based on TOGAF 9.At a
recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief
Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial
architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been
asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant
managers have expressed concern about the security and reliability of driving their MRPII and production
scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns
can be addressed.
Refer to the Rollins Manufacturing Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment architecture
project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many of the
participants have voiced concerns about the sweeping scope of the initiative. Others are confident that they
know a solution that will work. During the meeting, a number of alternative recommendations for how to
proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates
different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

which of the following is the best answer?

Scenario: Zephyr Enterprises
Please read this scenario prior to answering the question
Zephyr Enterprises specializes in the development of wind turbine blades for use in large-scale commercial
wind energy production systems. Zephyr has manufacturing facilities located in Palm Springs, California,
Omaha, Nebraska, and Winnipeg, Ontario. Each of these plants supplies a different manufacturer that builds
and sells complete systems. The turbine blades are custom engineered to meet each manufacturers design
specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However,
recent improvements in composite materials, coupled with enhanced automated methods for precision
application of materials during the molding process, have led to significant reduction in weight, increase in
strength, and greatly improved blade longevity. Zephyr has pioneered the development of a proprietary
automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the
process, but certain trade secrets must be closely guarded.Zephyr has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture
Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise
Architecture program.
Zephyr has used TOGAF and its Architecture Development Method (ADM) to develop its automated
manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies.
They have recently updated to TOGAF 9 and have adapted the Zephyr Enterprise Architecture to closely follow
the TOGAF 9 framework. All of Zephyrs IT architects have been trained and certified on TOGAF 9.Recently, an
architecture project was completed that defined a standard approach for controlling the Automated Test System
that is used at each plant to perform final quality assurance tests on each completed blade assembly. The
Manufacturing Architecture Board approved the plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy the new
Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a
uniform process be employed at each site to ensure consistency.
Refer to the Zephyr Enterprises Scenario:
You have been assigned by the Lead Architect for the Automated Test System controller project to conduct
Compliance Assessments at each manufacturing plant.
During the course of the assessment at the Omaha plant, you discover that the Distributed Data Acquisition
System they have purchased uses a proprietary Remote Procedure Call (RPC) that utilizes kernel mode
threads instead of the user mode threads that are specified in the Architecture Definition Document. In all other
respects, the system meets the requirements stated in the Architecture Definition Document and seems to
perform correctly.
You have been asked to describe the compliance of this system for the final report.
Based on TOGAF 9, which of the following is the best answer?


Page 27 of 157« First...1020...2526272829...405060...Last »