Complete the sentence. A gap analysis will enable the architect to do all of the following except
_____.

A.
identify building blocks that have been inadvertently omitted
B.
identify building blocks that have been intentionally eliminated
C.
identify building blocks to be carried over
D.
identify new building blocks that are needed
E.
identify potential vendors to provide new building blocks
TOGAF 9.1 book, section 27.2.
The answer is E.
0
0
The correct answer is D as it shows you the GAP or new building blocks required to fill that gap.