Which risk strategy is most important in this Fibre Channel infrastructure?

University IT provides shared Fibre Channel storage services. Disk, tape and fabric core are
located in the campus datacenter. Each college and department provides their own systems and
staff. The systems are co-located in the campus datacenter under controlled physical access.
Central IT provides fabric, storage and backup administration. Which risk strategy is most
important in this Fibre Channel infrastructure?

What is the most likely cause?

Infrastructure parameters include a small core edge design with all peripherals (disk and tape)
located in the core and all hosts connected to edge switches. Each host includes two HBAs, fabric
A and B respectively, with all disks visible on both fabrics and tape devices divided between
fabrics. The tape devices are single initiator zoned to LTO II tape drives. You are recovering a 200
GB journaling file system, 70% utilized; spread over eight mirrored spindles using 4×32 striping.
During recovery of one host, other hosts on the same edge report SCSI errors. What is the most
likely cause?

Where can the administrator check to see if errors occurred during the backup or recovery process?

A Solaris administrator responsible for backups is informed that the restore of data from the
backup appeared to be corrupt. The backups had appeared successful, but the database

administrator claims the data that was restored is invalid. Where can the administrator check to
see if errors occurred during the backup or recovery process?

Which option would allow for the addition of the new hosts while maintaining a redundant infrastructure?

A customer has deployed redundant switched fabrics in an environment which also includes nonHA, single-attached test servers. A new project requires additional connectivity for new HA
servers to be placed into production. There are not enough ports avalable on one of the existing
switches to complete an HA deployment. Which option would allow for the addition of the new
hosts while maintaining a redundant infrastructure?