why would the Quality Register be updated?

When producing an Exception Plan for a stage, why would the Quality Register be updated?

A.
The Quality Register is NOT updated when creating an Exception Plan

B.
To add details of any new quality management activities planned

C.
To close all quality checks from the Stage Plan that’s about to be replaced

D.
To record any corrective actions required when the quality checks of products in the current
Stage Plan were completed