Whose responsibility is it to assure the project’s stakeholders that the project remains desir seenagape 10 years ago Whose responsibility is it to assure the project’s stakeholders that the project remains desirable,viable and achievable at all times? A.Project Manager B.Corporate or programme management C.Senior User D.Executive ← Previous question Next question →