PRINCE2 Exam Questions

which to monitor project progress on a stage by stage basis?

Which product does the Project Board use as a base against which to monitor project progress on
a stage by stage basis?

A.
Stage Plan

B.
Project Plan

C.
Programme Plan

D.
Benefits Review Plan