Which task is performed by the Change Authority?

A.
Update the configuration management system when a change is approved
B.
Set a change budget
C.
Approve or reject a request for change within approved limits
D.
Refer changes that exceed budgetary limits to the Project Manager for approval
The answer C is right, Managing Successful Projects With PRINCE2, Section 9.3.1.1