Which statement is FALSE?

A.
A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
B.
A project’s output is any of the project’s specialist products
C.
A project benefit is only realized after the project has closed
D.
A project outcome is the result of the change derived from using the project’s outputs