Which statement applies to Stage Plans?

A.
Provide a baseline against which the Project Board monitor overall progress
B.
Assist the Project Manager in the day-to-day running and control of the project
C.
Are produced at the same time as the Project Initiation Documentation
D.
Always have the same duration as the Project Plan