PRINCE2 Exam Questions

which situation might the Controlling a Stage process be used?

In which situation might the Controlling a Stage process be used?

A.
Managing a long initiation stage of a complex project

B.
Managing the activities of a complex programme

C.
Managing support activities following the handover of the products to the operational
environment

D.
Creating an Exception Plan to replace the current Stage Plan