Which should be used to document any uncompleted work that needs to be done to a project product aft seenagape 10 years ago Which should be used to document any uncompleted work that needs to be done to aproject product after the project has closed? A. Follow-on action recommendations B. Issue Register C. Off-specifications D. Risk Register ← Previous question Next question →