Which should be funded from a change budget? seenagape 9 years ago Which should be funded from a change budget? A. The Starting up a Project process B. A fallback plan C. An agreed change to the scope of a project D. A change to a plan, within allocated tolerances, due to poor estimating Explanation: ← Previous question Next question →