PRINCE2 Exam Questions

Which project management team member represents the interest of those who will operate the project&#

Which project management team member represents the interest of those who will operate
the project’s products to realize the benefits after the project is complete?

A.
Senior User

B.
Senior Supplier

C.
Executive

D.
Project Manager