Which product would contain information on project and stage tolerance status, products completed du

Which product would contain information on project and stage tolerance status, products
completed during the period and a summary of actual or potential problems and risks?

A.
Product Status Account

B.
Communication Management Strategy

C.
Highlight Report

D.
Risk Register