which product does a Project Manager define the time and cost tolerances for the work to be done by seenagape 9 years ago In which product does a Project Manager define the time and cost tolerances for the work tobe done by a Team Manager? A. Stage Plan B. Product Description C. Team Plan D. Work Package ← Previous question Next question →