In which product does a Project Manager define the time and cost tolerances for the work to
be done by a Team Manager?
A.
Stage Plan
B.
Product Description
C.
Team Plan
D.
Work Package
You must be logged in to post a comment.
C
0
0
Answer D is right. Managing Successful Projects, A.26.2.