PRINCE2 Exam Questions

Which process is used by a Team Manager to coordinate work on one or more of the project’s pro

Which process is used by a Team Manager to coordinate work on one or more of the
project’s products?

A.
Initiating a Project

B.
Controlling a Stage

C.
Managing a Stage Boundary

D.
Managing Product Delivery