which process is it decided that an Exception Plan should be created to replace a Stage Plan? seenagape 8 years ago In which process is it decided that an Exception Plan should be created to replace a Stage Plan? A.Directing a Project B.Controlling a Stage C.Managing a Stage Boundary D.Closing a Project ← Previous question Next question →