Which process has a specific objective to record any information or lessons that can help later stag

Which process has a specific objective to record any information or lessons that can help later
stages of this project and/or other projects?

A.
Directing a Project

B.
Managing Product Delivery

C.
Managing a Stage Boundary

D.
Initiating a Project